CEMENT PLANT: MOTOR FAN

CASE STUDY

SMART IN FLOW CONTROL

Challenges

  • Plant has failures, unrepetitive, each time a different failure occurs in a different location.
  • ncrease visibility of plant. Failures occur in overlooked and ignored parts of plant.

How Product helped

  • Software created a very precise warning for Raw mill fan #4, out of ten fans.
  • After respective inspection, broken dampers were detected. Draft repair conducted immediately, reducing vibration. Complete repair is scheduled.

Value

  • Overlooked broken dampers were replaced thanks to SAM GUARD’s alerts. A significant damage to the raw mill fan was prevented.
  • By fixing a small problem ahead of time, a greater problem causing shutdown and lost production was eliminated.
  • $ 103,000 of damage prevented (1 day shutdown - 600,000 tons of cement per year/350 days of production x $ 60 per ton)